The 180 days after your engineer's report

2026-01-26 · 5 min

Week by week: bidding, board vote, permitting and repairs — and where the calendar usually slips.

The milestone report lands and the clock starts. Here is a realistic calendar for an occupied condominium tower in South Florida.

Weeks 1–4 — bidding

Send the report to three restoration contractors. Ask for line-item proposals with unit rates so the board can compare them without an engineer in the room.

Weeks 5–8 — board vote

Budget the vote, not just the work. Special assessments and reserve funding decisions take at least one meeting cycle.

Weeks 9–16 — permitting

Structural permits in Miami-Dade and Broward routinely take six to ten weeks. Nothing on site accelerates this.

Weeks 17–26 — repairs

Phased work on an occupied building, with a weekly photo report against the phase schedule agreed before mobilization.

Boards that start bidding in week one finish inside the county's window. Boards that wait for a second opinion before bidding usually do not.

No-cost building assessment

Send the report. We walk the building at no cost.

About 45 minutes on site, then a line-item proposal within 24 hours of the walkthrough. If the scope is not ours, we tell you on the spot and say who to call.

Florida license CGC1541097 · Verify at the Florida DBPR · General liability + workers' comp